Save the Scenic Santa Ritas

Fighting to protect the Santa Rita and Patagonia Mountains from the devastating impacts of mining.

  • Facebook
  • Twitter

Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
  • Home
  • About Us
    • Contact
    • Board of Directors and Staff
    • Endorsements
    • Opposition and Resolutions
    • Volunteers and Friends
  • Background
    • Rosemont Mine
      • History
      • Impacts
        • Air Quality
        • Land Use
        • Wildlife and Habitat
        • Scenic Views
        • Heritage
        • Recreation
        • Economy
        • Water and Hydrology
    • Legislation
    • Copper
    • Patagonia Area Mines
  • In the News
  • Action
    • What Can I Do?
    • Donate
    • Volunteer
    • Join Mailing List
    • Endorse Us
    • SSSR Presentation
    • Show Your Support
    • Letter Writing
  • Events
    • Past Events
  • Resources
    • Recommended Reading
    • Visual Media
    • Links
    • Documents and Reports
    • 1872 Mining Law
    • Inspiration
  • Projects
    • Lens on the Land
      • Biodiversity
      • Culture
      • Economy: Industry, Tourism & Recreation
      • The Land
      • Night Sky and Astronomy
      • Water Resources
    • Rosemont Mine Truth
  • Newsletter

Myth: The permitting process for the proposed Rosemont Mine is taking too long.

May 8, 2017 By santaritas 1 Comment

Myth:         The permitting process for the proposed Rosemont Mine is taking too long.

FACT:  First and most importantly, the devastating environmental impacts of the proposed Rosemont Mine are PERMANENT. Rosemont is proposing to dig an open-pit mine that is a half-mile deep and a mile rim-to-rim in the northern Santa Rita Mountains and pile potentially toxic mine waste 600-800 feet high in a watershed that provide 20% of the groundwater recharge for the Tucson basin.

The Arizona Game and Fish Department said that the proposed Rosemont Mine will “render the northern portion of the Santa Rita Mountains virtually worthless as wildlife habitat and as a functioning ecosystem…”

Any amount of time it takes to permit this mine, is inconsequential compared to the length of the impact on the lives of future generations.

Secondly, the actions and inactions of Rosemont and its owners are the major reason for the length of the permitting process for this project.

Consider:

  • Toronto-based Hudbay Minerals Inc., the owner of the Rosemont project, has failed to submit a mitigation plan to compensate for the destruction of wetlands, springs and seeps and important, functioning aquatic resources that meets the Clean Water Act’s requirements under Section 404 of the law. As a result, the Corps’ Los Angeles District Engineer last July recommended that the agency deny this required Clean Water Act permit consistent with repeated warnings by state and federal agencies that the project fails to comply with the law.
  • According to published reports in September 2012 (click here), the Coronado National Forest Supervisor requested that his staff review the veracity of information provided to it by Rosemont Copper Company. Specifically, as noted in the article, Rosemont provided information to the Coronado National Forest in early July indicating that dramatic increases in copper reserves would not result in additional water use, truck traffic or air pollution. However, in a subsequent September 12 letter to the Forest Supervisor, Rosemont backpedaled on some of those earlier assertions, thus leading to further questions about the company’s credibility and requiring that more staff resources be employed to investigate these discrepancies.
  • In August 2012, Augusta Resource released plans to significantly modify its mine proposal in an updated “Feasibility Study.” The Forest Service cited Augusta’s new plan as a reason to postpone the release of a Final Environmental Impact Statement (FEIS) and require additional analysis. (Source: click here)

Repeatedly throughout the regulatory consideration of the Rosemont Mine, agency staff criticized Augusta and Rosemont for not providing essential information in a timely manner. Consider these examples from documents released pursuant to the Freedom of Information Act (FOIA).

  • August 3, 2010 email from the Forest Service’s Debby Kriegel to colleagues said that, “[u]nfortunately, the DEIS schedule and Rosemont’s continued dawdling (we’ve been asking them since January to fund someone to develop recommendations for tree planting) [emphasis in the original] mean that this mitigation measure won’t show up in the DEIS.”
  • Notes from a July 27, 2010 Rosemont Team Meeting – The Forest Service noted during a Rosemont Team Meeting that Rosemont was late in providing certain required products was going to delay the project. Specifically, in the meeting notes regarding “Decisions Made” the Forest Service said that “[v]isual analysis- late products from RCC [Rosemont Copper Company] will extend project timeline”
  • Notes from a February 2010 Forest Service Rosemont Project Team Meeting – The Forest Service included a specific topic on the meeting outline noting “Timeline delays” and listed the “Reports needed from Rosemont”.
  • Notes from an August 11, 2009 Forest Service Rosemont Project Team Meeting – One of the topic discussed included, “Schedule slippage – possible reason include financial negotiation with RCC.”
  • Notes from an April 28, 2009 Forest Service Rosemont Project Team Meeting – Under “Topics Discussed” “Alternative and where to go next: Still waiting on Rosemont, SWCA [emphasis in the original] can continue work…” [Note: SWCA is the Forest Service’s NEPA consultant for the Rosemont Project.]
  • Notes from a March 24, 2009 Forest Service Rosemont Project Team Meeting – it was noted that with respect to alternatives, that only brainstorming could occur “because team is still waiting on vital reports.” Also, it was decided that the “Forest needs to document repeated requests for reports.”

Source:  Forest Service documents (click here.)

Thus, the examples cited above make it clear that Rosemont itself bears considerable responsibility for the length of time the permitting process has taken.

May 8, 2017

Filed Under: Documents and Reports, History, Key Facts, Rosemont, SSSR News

Recent Posts

  • Federal Memo May Bolster Hudbay’s Position on Rosemont Mine Site March 16, 2023
  • Hudbay Minerals Stock Tumbled 16% Last Week to US$4.55 per Share March 16, 2023
  • Hudbay Fights Order to Stop Grading at Mine Site Near Tucson March 16, 2023
  • THE HOT TOPIC: WATER OR LACK THEREOF January 24, 2023
  • Hudbay ramps up excavation for Copper World Complex as local resistance continues and expands January 7, 2023
  • Meet The Man Who Shoots At Birds All Day To Keep Them Off A Toxic Pit | World Wide Waste (video) January 5, 2023
  • Lithium America Mine Project Hampered After Judge Schedules Hearing on Nevada Mine January 5, 2023
  • Thousands Will Live Here One Day (as Long as They Can Find Water) January 5, 2023
  • Latest Updates About Local Water Issues and Rosemont / Copper World Mine Complex January 5, 2023
  • Hudbay, Forest Service won’t appeal ruling blocking Rosemont Mine December 19, 2022

Newsletter Sign-up

Sign up to receive important updates straight to your inbox! We will guard your privacy and will not provide your email to anyone else.

Rosemont/ Copper World Mine Complex News

Federal Memo May Bolster Hudbay’s Position on Rosemont Mine Site

Hudbay Fights Order to Stop Grading at Mine Site Near Tucson

THE HOT TOPIC: WATER OR LACK THEREOF

Hudbay ramps up excavation for Copper World Complex as local resistance continues and expands

Meet The Man Who Shoots At Birds All Day To Keep Them Off A Toxic Pit | World Wide Waste (video)

Lithium America Mine Project Hampered After Judge Schedules Hearing on Nevada Mine

More Posts from this Category

Hudbay Minerals Stock Tumbled 16% Last Week to US$4.55 per Share

 

Update on Lake Mead and Lake Powell water levels

All that rain and snow hammering the West surely means good news for water levels in Lake Mead and Lake Powell. Here’s a video update from last week with the current situation and expectations for the rest of the year.
WATCH NOW

Copper World Flyover January 6, 2023 by David Steele

Another shocking sight of the incredible destruction happening on our beautiful Santa Ritas.WATCH VIDEO NOW

Russ McSpadden’s recent fly-over showing mine activity

In Nov 2022 Russ captured recent bulldozing in the Santa Rita Mountains. His video starts over the Rosemont mine project on the east side and then swings over the Copper World project on the west side. WATCH VIDEO NOW

Explore the proposed Rosemont and Copper World projects virtually

Check out Pima County’s updated map of the proposed mine site. Click on any spot on the map for ownership/status information. Mapping details are based on Hudbay’s PEA dated May 1.

Proposed Rosemont/ Copper World Mine Complex

Image compilation of the area

LENS ON THE LAND

Recommended Reading List

Browse HERE over 30 titles of carefully selected books in various categories including: copper, water, mining, wilderness, exploration, and more. Your purchase supports the efforts of the SSSR

January 2023 Powerpoint Presentation

Click here to download (PDF)

Litigation Update

There have been two recent judicial rulings on the Rosemont Copper Company projects — one favorable and one unfavorable.

Click here to learn more

The latest on Hudbay’s Copper World project in the Santa Rita Mountains

Click here to download (PDF)

Where is the Rosemont/Copper World Mine Complex?

Click here for directions

HELP US PROTECT THE SANTA RITAS

DONATE

Copyright © 2023 · Save the Scenic Santa Ritas